HY-10 Ramsey Improvement IP #23-12

  1. Construction Updates
  2. Project Updates

September 25, 2023

To date the Contractor has placed the first lift of bituminous pavement and completed the majority of restoration in the boulevard areas.

During the week of September 25, the Contractor is anticipated to complete the seeding in the boulevard areas and place the final lift of bituminous pavement. The paving has not yet been scheduled but will likely occur later in the week.

August 31, 2023

During the week of August 21, the Contractor finished fine grading the aggregate base and placed the majority of concrete curb and gutter. On August 30, the Contractor placed the first lift of new bituminous pavement.

The Contractor is working on setting up the remaining concrete driveways, sidewalk, and curb and gutter. They are currently scheduled to pour the remaining concrete during the week of September 5, this includes the concrete median in Bunker Lake Boulevard.

Restoration of the impacted boulevard areas begin August 31 and is anticipated to take 2 – 3 weeks to complete. The final lift of bituminous pavement will be placed after restoration is complete but has not yet been scheduled.

August 10, 2023

To date, the contractor has completed all Watermain and Sanitary Sewer construction. Testing of the new watermain and sewer is required before it is put into service. Construction on the storm sewer has begun and is anticipated to be complete by August 14.

After the storm sewer construction is complete, the contractor will begin grading the subgrade prior to the installation of the new concrete curb and gutter. The concrete curb and gutter are scheduled to be placed starting August 22. However, this is subject to change.