Xenon Street NW Culvert Replacement August 20-24, 2018

The City of Ramsey is replacing a failing 36 inch metal culvert running across Xenon Street between Azurite Court NW and Nowthen Blvd. The scope of this work includes removal of the existing culvert and bituminous pavement as necessary, installation of a new culvert of the same size and to the same location, and restoration of the roadway and disturbed areas. 

Construction is planned to occur August 20 - 24, 2018. The road closure date signs will be placed 10 days prior to closure. As always, this work is weather dependent. 

  • Construction update letter mailed to the affected property owners on August 9, 2018.
  • On Monday, August 20, 2018 Reshetar Systems began construction on Xenon Street between Azurite Court NW and Nowthen Blvd. The Contractor anticipates culvert replacement and road closure will take 1 week to complete, weather depending.
  • Construction is substantially complete August 31, 2018.