Stanhope Terrace St Reconstruction IP 18-00 (Updated May 15, 2018)

  • Approximately 0.5 miles of streets will be reconstructed using a full-depth reclamation (FDR) process.
  • Streets will primarily remain open to traffic during construction.
  • Construction update letters will be mailed to affected property owners during construction. 
  • Concrete curb and gutter will be poured along both sides of streets and around cul-de-sacs on Wednesday, May 16.
  • Concrete valley gutter will be poured across intersections on Thursday, May 17.
  • While driveways are not accessible (May 16 to approximately May 23) parking will be allowed overnight on all streets.
  • Vehicles will also be allowed to park overnight on adjacent side streets across Roanoke Street and Alpine Drive without being ticketed.
  • Construction will be substantially complete by June 1, 2018.
  • Final completion will occur in 2019.